Please note that we are beginning rehabilitation work starting June 9th on the following streets:
– Boulevard du Lac between 9e Avenue and 15e Avenue
– 10e Avenue south of boul. du Lac
– 11e Avenue south of boul. du Lac
In the coming weeks, work will also begin on the following streets:
– Boulevard du Lac between 15e Avenue and Crescent
– Lakewood
– Lakeview
– Hudson between 17e Avenue and 18e Avenue
– 17e Avenue between Hudson and boul. du Lac
– 24e Avenue between chemin d’Oka and the southern limit
– du Belvédère
– Marquette between 8e Avenue and Olympia
– Olympia
– Henri-Brabant
– 9e Avenue between Caron and Guy
Work should be completed by the end of September. A temporary supply network will be established to supply drinking water to homes affected by the work.
In case of emergency, you can contact the Territory Management Department at 450 473-4688. Outside administrative office operating hours, you can reach the Sanexen contractor at1-866-943-4066.
Regarding fire safety, please note that non-working fire hydrants will be replaced with temporary hydrants. Non-working fire hydrants will be covered with bags.